PERBANDINGAN WAKTU RENCANA PELAKSANAAN KEGIATAN DENGAN METODE KONVENSIONAL DAN METODE PERT
Comparison of Activity Implementation Plan Time with The Conventional And The Pert Method
DOI:
https://doi.org/10.59896/gara.v19i4.423Keywords:
Project, PERT Method, ConventionaI Method, Duration PlanAbstract
The implementation of the Road and Bridge Preservation Project in several districts in Bali, namely Gianyar, Bangli, Klungkung, and Karangasaem, experienced a setback in the 18th week by 4%. In the implementation, a design change caused a volume change and caused delays. The purpose of this study was to compare the implementation plan with the conventional method and the PERT method with Microsoft Project. This method is often used in project planning using a network that requires three time estimates: the most likely, optimistic, and pessimistic. The data used were the Budget Plan data, the Time Schedule (planning time), the work calendar, and the interview results related to the percentage of success of activity time from the contractor. The data were analyzed with Microsoft Excel to obtain the optimistic, pessimistic, and most likely times. Based on the PERT analysis, data processing was then continued with Microsoft Project to produce the optimal time. The planning time obtained using the conventional method is 226 days, and using the PERT method, the optimistic planning time is 215 working days, the pessimistic planning time is 246.5 working days. The optimal planning time is 227.58 working days. The implementation time of the PERT method analysis is 1.58 days longer than that of the conventional method
References
Atkinson, R. 1999. Project management: cost, time and quality, two best guesses and phenomenon, its time to accept other success criteria. 17(6): 337–342.
Departemen Pekerjaan Umum. 2010. Pedoman Teknis Pembangunan Jalan. Jakarta: Direktorat Jenderal Bina Marga.
Discenza, R., Forman, J.B. 2007. Seven Causes of Project Failure. Project Management Institute, .
Ervianto, W.I. 2002. Manajemen Proyek Konstruksi, Edisi Pertama. Salemba Empat, 2002.
Hendrickson, C., & Au, T. 2008. Project Management for Construction: Fundamental Concepts for Owners, Engineers, Architects, and Builders. Prentice Hall.
Kementerian PUPR. Peraturan Menteri PUPR Nomor 11/PRT/M/2020 tentang Pedoman Teknis Pembangunan Jalan dan Jembatan. , (2020).
Kerzner, H. 2017. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. In 12th Edition. John Wiley & Sons Inc.
Mulyono, A.T. 2004. Teknologi Bahan dan Perkerasan Jalan Raya. Yogyakarta: Beta Offset.
PUPR. 2020. Pedoman Penggunaan Perangkat Lunak dalam Manajemen Proyek Konstruksi. Jakarta: Ditjen Bina Konstruksi.
Siregar, A. 2018. Manajemen Proyek Konstruksi: Perencanaan, Penjadwalan, dan Pengendalian Proyek. Jakarta: Mitra Wacana Media.
Snyder, C. S., & Kline, C. 2012. A User’s Manual to the PMBOK Guide. Project Management Institute.
Soeharto, I. 1998. Manajemen Proyek. Jakarta: Erlangga.
Sukirman, S. 1999. Perkerasan Lentur Jalan Raya. Bandung: Nova.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Ni Luh Made Ayu Mirayani Pradnyadari, I Gede Ngurah Sunatha, Ni Made Bakti Pratiwi

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.